Build It on a Board First#
The Pneumatics Manual recommends assembling and testing the whole system on a bench-top board before it ever goes on the robot. You will plumb two sub-assemblies that meet at the regulator.
High-Pressure Side Build Order#
Following the Manual's documented steps:
- Compressor + relief valve. Thread a 1/8 in hex nipple into the compressor output, add a 1/8 in union tee, attach the pressure relief valve (via a suitable adapter) directly to the compressor with hard fittings, and put a push-to-connect fitting on the remaining tee port. The relief valve must be hard-mounted to the compressor — no tubing between them.
- Pressure switch, gauge, and vent valve. Build a small tree of union tees and hex nipples carrying the pressure switch (or analog sensor), the stored-pressure gauge, and the vent valve so you can dump air by hand.
- Air storage tank(s). Run tubing from the compressor/relief assembly through a union tee to the tank.
- Primary regulator. Run tubing from the tank to the inlet of the regulator; install push-to-connect fittings in the inlet and outlet, attach the working-pressure gauge, and plug any unused port. This regulator is the boundary to the working side.
Working-Pressure Side Build Order#
- Solenoid valve. Thread push-to-connect fittings into valve ports 1, 2, and 4 and connect the valve's two wires (for a double solenoid) to the controller.
- Actuator. Fit push-to-connect fittings to both cylinder ports.
- Connect them. Tube from the regulator outlet to valve port 1 (supply); tube from valve ports 2 and 4 to the cylinder's two ports.
Plumbing Technique#
- Threaded joints: one wrap of PTFE tape biased toward the component, tightened with wrenches.
- Push-to-connect: cut tubing square, leave slack so joints are not strained, and push the tube fully home until it seats. To remove, press the colored collar in and pull the tube out.
- Heat management: keep tubing away from the hot compressor; the Manual suggests extra brass fittings as a heatsink near the compressor during heavy use.
Result#
When finished you have a complete loop: the compressor charges the tank toward 120 psi, the regulator delivers up to 60 psi to the valve, and the valve drives the cylinder. Next you will verify it is safe and leak-free.
the part worth keeping
Key takeaways
- Build and test on a bench board before mounting on the robot.
- High side order: compressor + hard-mounted relief valve, then switch/gauge/vent tree, then tank, then primary regulator.
- Working side: solenoid valve (ports 1/2/4) to the double-acting cylinder, fed from the regulator outlet.
- Use one wrap of PTFE tape on threads and seat push-to-connect tubing fully and square to prevent leaks.
Mechanical, Build & PneumaticsBuilding, Wiring, and Programming a Pneumatic Systemlesson 1 of 4
Keep going
Take the quiz+10 XP with an accountMore in Building, Wiring, and Programming a Pneumatic System
where this came from
Sources and corrections
This lesson is AI-assisted: drafted from primary sources, then reviewed and edited by hand. Errors still get through. When one is reported we fix it and write down what changed, in public, in the corrections log.
sources and further reading
- firstinspires.orgFIRST Pneumatics Manual (Plumbing a Basic Pneumatics Setup)
- frczero.orgFRC Zero - How to Set Up a Pneumatic System
clipped to this lesson
Articles that go further on this
The lesson gets you through the topic. These go wider on it, and they read in one sitting.
- 7 min readFRC "No Robot Code" & Driver Station Won't Connect: Full Fix ChecklistA verified, step-by-step FRC troubleshooting decision tree for "No Robot Code" and a Driver Station that won't connect to the roboRIO — most common causes first./blogread it
- 4 min readFRC Drivetrain Types: Tank, Swerve, and MecanumA beginner-friendly guide to FRC drivetrains: how tank, swerve, and mecanum drives work, their tradeoffs, and how to pick one for your robot./blogread it
- 9 min readFRC Pneumatics: How to Design, Wire, and Program a Pneumatic SystemComplete FRC pneumatics guide: components, the REV Pneumatic Hub vs PCM, single vs double solenoids, safe wiring, WPILib programming, and the 60/120 psi limits./blogread it
answer sheet
Lesson quiz
All 3 right completes the lesson. Miss one and only that question comes back, anything you already answered correctly stays banked.
0 of 3 answered
01Downstream of the regulator, what is the maximum working pressure this circuit delivers to the solenoid valve and cylinder?
02In the high-pressure side build order, how must the pressure relief valve be attached?
03Which statement correctly describes the two pressure zones the regulator creates in this circuit?
Answer every question to submit.
All 47 lessons in Mechanical, Build & Pneumaticsopenclose
01 / prerequisites
02 / drivetrains
03 / power-transmission
04 / structure-materials-fasteners
05 / mechanisms-fabrication-assembly
06 / pneumatics-fundamentals
07 / pneumatic-components
08 / build-wire-program
09 / safety-rules-testing
10 / worked-examples-mini-projects
- Not read yet:Mini-Project 1: A Single-Jointed Arm From Math to Motion
- Not read yet:Mini-Project 2: A Two-Stage Cascade Elevator
- Not read yet:Mini-Project 3: A Velocity-Controlled Flywheel Shooter
- Not read yet:Mini-Project 4: A Pivoting Roller Intake
- Not read yet:Mini-Project 5: Integrating a COTS Swerve Module
11 / common-mistakes-troubleshooting
- Not read yet:Pneumatics Won't Fire: A Full Diagnostic Tree
- Not read yet:The Robot Won't Drive Straight (and Other Drivetrain Sins)
- Not read yet:Gearboxes That Grenade and Fasteners That Vibrate Loose
- Not read yet:Closed-Loop Mechanisms That Oscillate, Sag, or Stall
- Not read yet:Field-Ready Reliability: Inspection, Spares, and the Pit Checklist
12 / advanced-techniques-case-studies
- Not read yet:Characterizing Any Mechanism with SysId
- Not read yet:Simulation-Driven Design with WPILib Physics Models
- Not read yet:Motion Profiling and Superstructure Coordination
- Not read yet:Designing for Weight, Stiffness, and Manufacturability
- Not read yet:Case Studies: Learning From Open Alliance Robots